Priority | Item | Tasks | Assignee | Initial Size Estimate | Day 1 | Day 2 | Day 3 | Day 4 | Day 5 | Day 6 | Day 7 |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Project configuration | Repository Setup Dependencies CI |
Team | 1 1 1 |
1 1 1 |
0 0 1 |
0 0 0 |
/ | / | / | / |
2 | Project design | Requirement Definition Architecture Definition |
Team | 4 2 |
4 2 |
4 2 |
4 2 |
0 2 |
0 0 |
/ | / |
3 | Documentation structure | Team | 2 | 1 | 1 | 0 | / | / | / | / |
This first sprint’s goal is to define the project’s main structure, defining the core elements, their expected use, functions and interactions.
This sprint’s deadline is set for 22/06/2025.
An initial diagram was drawn for a more as-a-whole understanding of the project to be.
A consensus was met for how code, documentation and resources should be written.
This was a bumpy start, due to overlapping work this sprint’s throughput has not been consistent, although it is expected since this first phase requires every member’s participation.