| Priority | Item | Tasks | Assignee | Initial Size Estimate | Day 1 | Day 2 | Day 3 | Day 4 | Day 5 | Day 6 | Day 7 |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | DSL Method Ordering | Enforcing method ordering during game creation | Agosta | 8 | 8 | 3 | 0 | / | / | / | / |
| 2 | Preparing for release | Generating executable app Completing documentation Preparing a demo |
Team Team Team |
1 7 2 |
1 7 2 |
1 7 1 |
/ / 0 |
/ / / |
/ / / |
/ / / |
/ / / |
This sprint’s goal is to complete the project by implementing the last optional feature and preparing for a product showcase.
This sprint’s deadline is set for 14/07/2025.
We have been able to complete all task at hand.
No more sprints are needed, since the project is complete.
We’ve found no issues in this last sprint.